Tooling Manufacture Schedule |
||||||
Customer | Happy Customer | |||||
Part No. | R860701, R860702 (Zinc) | |||||
Part Name | M HSNG FNT, M HSNG BACK (Zinc) | |||||
Date | 9/14/2009 | |||||
Procedure | May | June | ||||
Tooling Design | 5/12~5/15 | |||||
Design Complete/Approval | 5/15~5/17 | |||||
Tooling Material Preparation | 5/18~5/20 | |||||
Tool base Machining | 5/21~5/23 | |||||
Heat treatment | 5/24~5/26 | |||||
Electrode Machining | 5/27~5/29 | |||||
Tool Insert fine Machining | 5/30~6/2 | 5/30~6/2 | ||||
EDM | 6/3~6/5 | |||||
Polishing | 6/6~6/8 | |||||
Die fitting | 6/10~6/11 | 6/10~6/11 | ||||
Assembly | 6/12~6/14 | |||||
Tool Trial | 6/15~6/16 | |||||
Machining + Painting | 6/17~6/25 |